Why it keeps happening

Treatment works capacity

Every overflow goes to a sewage treatment works that serves a fixed area. There is no public data available to understand if the works has sufficient capacity to treat the sewage for the local population. We estimate this capacity based on the required capacity in the EA permit compared to the local population estimated to be on the sewage system. As we receive data on the actual processing capacity from South West Water we will add that too.

Capacity across the River Teign

None of the 13 works we track are estimated to be over its permitted flow. We are waiting to receive permits for 13 works and hence cannot yet assess their capacity.

0
Over their permitted flow
estimated load above the permit
5
Have headroom but spill anyway
points to another problem
13
Cannot be assessed
no permit received yet
0
People on an over-loaded works
served by works over or at the limit
Works
Load against permit
Overflow at works
Spare capacity
Compton System
population unknown · permit not found
Not known
Not assessed
1 h
1 upstream · 1,431 pre-STW
Not known
Newton Abbot System
population unknown · permit not found
Not known
Not assessed
3,904 h
29 upstream · 1,830 pre-STW
Not known
Moretonhampstead System
population unknown · permit not found
Not known
Not assessed
1,156 h
7 upstream · 484 pre-STW
Not known
Chagford System
population unknown · permit not found
Not known
Not assessed
385 h
6 upstream · 1,016 pre-STW
Not known
Tedburn St Mary System
population unknown · permit not found
Not known
Not assessed
492 h
1 upstream · 36 pre-STW
Not known
Whiddon Down System
population unknown · permit not found
Not known
Not assessed
0 h
0 upstream
Not known
Throwleigh System
population unknown · permit not found
Not known
Not assessed
56 h
0 upstream
Not known
Tedburn System
population unknown · permit not found
Not known
Not assessed
439 h
0 upstream
Not known
Ipplepen System
population unknown · permit not found
Not known
Not assessed
769 h
0 upstream
Not known
Chudleigh K System
population unknown · permit not found
Not known
Not assessed
580 h
0 upstream
Not known
Teign Valley System
population unknown · permit not found
Not known
Not assessed
4,622 h
0 upstream
Not known
Cheriton Bishop System
population unknown · permit not found
Not known
Not assessed
512 h
1 upstream
Not known
Denbury System
population unknown · permit not found
Not known
Not assessed
363 h
0 upstream
Not known

The black line marks 100% of permitted dry-weather flow; a dashed empty bar means no permit was found to measure against. Load is an estimate — population served × per-head water use, plus infiltration — not a permit-compliance finding. A works over 100% here is a signal to investigate, not a proven breach. Overflow hours are the works' own storm overflow in the last full year.

13 works awaiting a permit

We are still waiting to receive permits for Compton System, Newton Abbot System, Moretonhampstead System, Chagford System, Tedburn St Mary System, Whiddon Down System and others, so we cannot yet check whether they are big enough for the population they serve. This is a gap in the public record — not a clean bill of health — and it is the quickest thing on this page to fix: the permitted flow is public information a water company must supply on request.

Why this matters for reading spills

Works over capacity

If a works cannot treat the flow it receives, it spills to protect itself. The remedy is capital investment or a lower permitted load — years and millions, but it is the water company's to fix.

Headroom, but still spills

A works with spare capacity whose network still spills points to another problem — often something on that branch, like a blockage, a failed pump, or groundwater getting into the sewer. Frequently cheap to fix, and fixable now.

No permit found

Where we cannot find the permitted flow, the works cannot be assessed at all. That is a gap in the public record, and closing it is the first step to holding capacity to account.

How growth becomes spills

A developer has a section 106 right to connect to the public sewer, and the water company has a section 94 duty to accept the flow — but capacity is only funded on a five-yearly capital cycle. New connections can therefore arrive years before the works is enlarged to take them, and the overflow absorbs the gap. Schedule 3 to the Flood and Water Management Act 2010, which would make sustainable drainage mandatory and give a SuDS Approving Body a say, has been in force in Wales since 2018 but remains uncommenced in England — so here there is no such body.

What the permit actually sets

The permitted dry-weather flow is set by Formula A — roughly DWF + 1,360 × population + 2 × trade effluent (litres/day). The permit also sets a flow to full treatment, typically about three times DWF, below which everything must be treated rather than spilled. Our load figure compares estimated demand against that permitted DWF. 13 works in the catchment publish no permitted flow at all, so their load cannot be calculated — they show as not assessed, never 0%.